Question:The following schedule is a display of what type of analysis? Amount Percent Current Assets $200,000 25% Property, Plant and equipment $600,000 75% Total Assets $800,000
A Horizontal analysis
B Differential analysis
C Vertical analysis
D Ratio analysis
+ AnswerC