Question:A can do a piece of work in 6 days and B alone can do it in 8 days. A and B undertook to do it for Rs. `640`. With the help of C, they finished it in 3 days. How much is paid to C ? 

A `Rs. 75` 

B `Rs. 80` 

C `Rs. 120` 

D `Rs. 160` 