Question:A and B can separately do a piece of work in 20 and 15 days respectively. They worked together for 6 days, after which B was replaced by C. If the work was finished in next 4 days, then the number of days in which C alone could do the work will be :
+ Explanationsolution:
`(A + B)'s 6` day's work `= 6(1/20 + 1/15)`
`= 7/10`.
`(A + C)'s 4` day's work `= 3/10`.
`(A + C)'s 1` day's work `= 3/40`
`A's 1` day's work `= 1/20`
`:. C's 1` day's work `=(3/40 - 1/20)`
`=1/40`.
Hence, C alone can finish the work in `40` days.