Question:With the job order cost system, a credit balance in the Factory Overhead account at the end of an accounting period would indicate: 

A that an error in the job cost system has occurred. 

B that the company lost money during the period. 

C the presence of under-applied overhead. 

D the presence of over-applied overhead. 