Question:If A, B and C together can finish a piece of work in 4 days; A alone can do it in 12 days and B in 18 days, then C alone Can do it in:
A 21 days
B 16 days
C 14 days
D 9 days
/47
+ Answer
D
+ Explanationsolution:
`(A + B + C)`'s 1 day's work =`1/4`
`(A + B)`'s 1 day's work =`(1/12 + 1/18)`
=`5/36`.
C's 1 day's work =`(1/4 - 5/36)`
=`4/36`
=`1/9`.
`:.`C alone can finish the work in 9 days.