Question: 12 men can complete a work in 18 days. Six days after they started working, 4 men joined them. How many days will all of them take to finish the remaining work ?
A
B
C
D
9
B
10
C
12
D
15
Note: solution:
`(12 xx 18)` men can complete the work in 1 day.
`:. 1` man's 1 day's work `= 1/216`.
`12`men's 6 day's work `= (1/18 xx 6)`
`= 1/3`.
Remaining work `=(1 - 1/3)`
`= 2/3`.
`16` men's 1 day's work `= 16/216`
`= 2/27`.
`2/27` work is done by them in 1 day.
`2/3` work is done by them in `(27/2 xx2/3)`
`= 9` days.